Substation Scout

Gibbons Creek

Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Harris County. First named in the release with data as of February 1, 2015.

Harriscounty as printed
345kV
CNPutility
3projects listed

No HIFLD substation record has this name in this county (a record of the same name exists in another county).

Generation interconnection requests filed in Harris, TX: ERCOT queue, 30 active of 35 · MISO queue, 0 active of 1. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
This models upgrades required for a proposed load addition
Install new 345 kV CEHE-owned sub. Loop on 345 kV Zenith to Gibbons Creek Ckt.18 & 50
ERCOT project 110086A
CNP
Tier 4
Conceptual
Future tab
345 Jul 2028 Becker to Zenith/Gibbons Creek
Harris County
Becker, Zenith, Gibbons Creek
This models upgrades required for a proposed load addition
Install new customer 345 kV sub. Loop into new 345 kV CEHE sub with two leads each 3.6 miles.
ERCOT project 110086B
CNP
Tier 4
Conceptual
Future tab
345 Jul 2028 NEWSUB to Zenith/Gibbons Creek
Harris County
Zenith, Gibbons Creek
Additional Facility Ratings Methodology Phase 2 (FRM2) Substation Upgrades.
Upgrade Ckt.50B Zenith to Gibbons Creek to increase thermal limits as part of FRM2 upgrades.
ERCOT project 99791A
CNP
Tier 4
Planned
Current-year planned tab
345 Nov 2026 Zenith to Gibbons Creek
Grimes / Harris County
Zenith, Gibbons Creek

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 202699791AProjected in-service dateJun 2026 → Nov 2026
July 13, 2026110086AFirst listedon the Future tab
July 13, 2026110086BFirst listedon the Future tab
July 13, 202699791AProjected in-service dateMay 2026 → Jun 2026
June 1, 202699791AMoved between tabsFuture → Current-year planned
June 1, 202699791AProjected in-service dateOct 2029 → May 2026
October 1, 202599791AFirst listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first