Garrott

Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Harris County. First named in the release with data as of October 1, 2016.

Harriscounty as printed
138kV
CNPutility
3projects listed

A HIFLD substation record has the same name and county: GARROTT (HARRIS County). The names agree; that does not confirm they are the same facility.

Generation interconnection requests filed in Harris, TX: ERCOT queue, 30 active of 35 · MISO queue, 0 active of 1. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Heights 138kV Loop Conversion
Tap existing Ckt.90A Kirby to Garrott near Tower 34720 to serve Dunlavy transformer TR3 load. Create Ckt.90A Kirby tap to DN-TR3 tap to Garrott.
ERCOT project 73578G
CNP
Tier 4
In-Service
Completed tab
138 May 2025
actual 2025-05
Kirby to Garrott
Harris County
Kirby, Garrott
Upgrade to increase thermal limits as part of FRM upgrades
Upgrade Hyde Park to Downtown Ckt.32A to increase thermal limits as part of FRM upgrades
ERCOT project 87479I
CNP
Tier 4
Conceptual
Current-year planned tab
138 Jul 2025 Kirby to Garrott
Harris County
Kirby, Garrott
Facility Ratings Methodology (FRM) Upgrades
Upgrade Kirby to Garrott Ckt.37A to increase thermal limits as part of FRM upgrades
ERCOT project 90232H
CNP
Tier 4
Planned
Current-year planned tab
138 Oct 2026 Kirby to Garrott
Harris County
Kirby, Garrott

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 202687479IStatus as reportedPlanned → Conceptual
July 13, 202690232HProjected in-service dateJul 2026 → Oct 2026
June 1, 202673578GStatus as reportedPlanned → In-Service
February 1, 202690232HMoved between tabsFuture → Current-year planned
June 1, 202573578GMoved between tabsFuture → Completed
June 1, 202587479IMoved between tabsFuture → Current-year planned
June 1, 202590232HProjected in-service dateJul 2025 → Jul 2026
February 1, 202590232HFirst listedon the Future tab
October 1, 202473578GFirst listedon the Future tab
October 1, 202487479IFirst listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.