Fry Road

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Harris County. First named in the release with data as of February 1, 2015.

Harriscounty as printed
138kV
CNPutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Harris, TX: ERCOT queue, 30 active of 35 · MISO queue, 0 active of 1. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Expand Zenith substation with addition of 35kV Distribution Facilities. Tap TR1 on Ckt.09J to create new Ckt.09J Zenith to Zenith TR1 tap to Fry Road tap. Tap TR2 on Ckt.76A to create new Ckt.76A Zenith to Zenith TR2 tap to Fry Road tap.
ERCOT project 75938
CNP
Tier 4
In-Service
Completed tab
138 Oct 2025
actual 2025-03
Zenith to Fry Road
Harris County
Zenith, Fry Road

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
February 1, 202675938Moved between tabsCurrent-year planned → Completed
February 1, 202675938Status as reportedPlanned → In-Service
June 1, 202575938Moved between tabsFuture → Current-year planned
February 1, 202575938Projected in-service dateMay 2025 → Oct 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first