BACLIF
Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Galveston County. First named in the release with data as of May 12, 2023.
Galvestoncounty as printed
138kV
CNPutility
1projects listed
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Galveston, TX: ERCOT queue, 11 active of 13. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| PH Robinson Area 138kV Upgrades Reposition existing PH Robinson to BACLIF generator lead from the PHR_South bus to the PHR_North bus. ERCOT project 73352A |
CNP Tier 4 |
Planned Future tab |
138 | Dec 2027 | PH Robinson to BACLIF Galveston County |
PH Robinson, BACLIF |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2025 | 73352A | Projected in-service date | Oct 2026 → Dec 2027 |
| June 1, 2025 | 73352A | Projected in-service date | May 2026 → Oct 2026 |
| February 1, 2025 | 73352A | Projected in-service date | Dec 2025 → May 2026 |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.
Site Scanner