Substation Scout

FPP Yard 2

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Fayette County. First named in the release with data as of October 1, 2024.

Fayettecounty as printed
345kV
LCRATSCutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Fayette, TX: ERCOT queue, 4 active of 5. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
FPP Yard 2 - Lytton Springs Transmission Line Overhaul
LCRA TSC will overhaul FPP Yard #2 - Lytton Springs 345-kV transmission line T255 to ensure structural integrity of the circuit. Engineering will review this transmission circuit for scope including hardware/insulator integrity, structural load issues, need for containment (dead-ends) structures, and clearances at highway and railroad crossings.
ERCOT project 85963 · RPG 24RPG013
LCRATSC
Tier 4
Planned
Completed tab
345 May 2026
actual 2026-05
FPP Yard 2 to Lytton Springs
Fayette / Caldwell County
FPP Yard 2, Lytton Springs

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 202685963Moved between tabsCurrent-year planned → Completed
February 1, 202685963Moved between tabsFuture → Current-year planned
October 1, 202485963First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.