Reiter

Named in 4 listed projects in ERCOT’s transmission project tracking workbook, in Ector County. First named in the release with data as of October 1, 2022.

Ectorcounty as printed
138, 345kV
ONCORutility
4projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Ector, TX: ERCOT queue, 21 active of 25 · SPP queue, 0 active of 6. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Reiter - Tesoro 345 kV Double-Circuit Line
Construct new 2.5-mile 345 kV double-circuit line from Tesoro to Reiter
ERCOT project 71187 · utility no. R8629 · RPG 23RPG029
ONCOR
Tier 1
Planned
Current-year planned tab
345 Dec 2026 Tesoro to Reiter
Midland / Ector County
Tesoro, Reiter
Salt Flat Road 138 kV Switch and Salt Flat Road - Barr Ranch - Reiter 138 kV Second Circuit
Add Salt Flat Road 138 kV Switch and Salt Flat Road - Barr Ranch - Reiter 138 kV Second Circuit & De-energize auto at Odessa EHV
ERCOT project 81175 · utility no. R8704 · RPG 25RPG007
ONCOR
Tier 3
Planned
Completed tab
138 Dec 2025
actual 2025-12
Reiter to Salt Flat Road
Ector / Midland County
Reiter, Salt Flat Road
Reiter to Yarbrough 138 kV Line Rebuild
Rebuild the existing138 kV line from Reiter to Yarbrough
ERCOT project 81418 · utility no. R8527 · RPG 25RPG008
ONCOR
Tier 3
Planned
Current-year planned tab
138 Dec 2026 Reiter to Yarbrough
Ector / Crane County
Reiter, Yarbrough
Rebuild Odessa EHV - Reiter 138 kV Double Circuit Line
Add Permian Basin Reliability Plan Upgrade ID L17 Upgrade Odessa - Reiter 138kV double-circuit line
ERCOT project 93466 · utility no. PB L17
ONCOR
Tier 3
Planned
Future tab
138 Dec 2027 Odessa EHV to Reiter
Ector County
Odessa EHV, Reiter

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
February 1, 202671187Moved between tabsFuture → Current-year planned
February 1, 202681175Moved between tabsCurrent-year planned → Completed
February 1, 202681418Moved between tabsFuture → Current-year planned
October 1, 202571187Projected in-service dateMay 2027 → Dec 2026
October 1, 202581418Projected in-service dateDec 2027 → Dec 2026
June 1, 202581175Moved between tabsFuture → Current-year planned
June 1, 202593466First listedon the Future tab
February 1, 202581418Projected in-service dateDec 2026 → Dec 2027
June 1, 202471187Projected in-service dateDec 2026 → May 2027
June 1, 202481175First listedon the Future tab
June 1, 202481418First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.