Substation Scout

Averitt

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Ector County. First named in the release with data as of October 1, 2025.

Ectorcounty as printed
345kV
ONCORutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Ector, TX: ERCOT queue, 21 active of 25 · SPP queue, 0 active of 6. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Oncor_FW_81410_Averitt Synchronous Condenser
Add Averitt Switch Synchronous Condenser
ERCOT project 81410 · utility no. D20231 · RPG 23RPG029
ONCOR
Tier 1
Planned
Current-year planned tab
345 Aug 2026 Averitt to Averitt
Ector County
Averitt

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202681410Moved between tabsFuture → Current-year planned
October 1, 202681410Projected in-service dateMar 2027 → Aug 2026
June 1, 202681410Projected in-service dateJan 2027 → Mar 2027
February 1, 202581410Projected in-service dateDec 2026 → Jan 2027
June 1, 202481410First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.