Pitchfork
Named in 4 listed projects in ERCOT’s transmission project tracking workbook, in Dickens County. First named in the release with data as of October 1, 2025.
Dickenscounty as printed
345kV
WETTutility
4projects listed
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Dickens, TX: ERCOT queue, 9 active of 10. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Ad Hoc TPIT: 432 MVAR Reactive Compensation at Pitchfork 345 kV ERCOT project 110591 |
WETT Tier 4 |
Conceptual Future tab |
345 | Sep 2029 | Pitchfork 34k kV to Pitchfork 345 kV Dickens County |
Pitchfork 34k kV, Pitchfork |
| Build approximately 94.5-mile 345 kV double circuit line from Buck Canyon to Pitchfork substation ERCOT project 110851 |
WETT Tier 1 |
Conceptual Future tab |
345 | Dec 2029 | Buck Canyon 345 kV to Pitchfork 345 kV Borden / Dickens County |
Buck Canyon, Pitchfork |
| WETT Pitchfork 345 kV Station for Synchronous Condensers ERCOT project 112695 · RPG 25RPG005 |
WETT Tier 3 |
Under Construction Future tab |
345 | May 2027 | Cottonwood to Pitchfork Dickens County |
Cottonwood, Pitchfork |
| WETT Pitchfork Synchronous Condenser ERCOT project 87635 · RPG 23RPG026 |
WETT Tier 1 |
Under Construction Future tab |
345 | Sep 2027 | Pitchfork to Pitchfork Dickens County |
Pitchfork |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 112695 | First listed | on the Future tab |
| July 13, 2026 | 110591 | Projected in-service date | Sep 2028 → Sep 2029 |
| July 13, 2026 | 110851 | First listed | on the Future tab |
| July 13, 2026 | 110591 | First listed | on the Future tab |
| June 1, 2026 | 87635 | Status as reported | Planned → Under Construction |
| June 1, 2025 | 87635 | Projected in-service date | Oct 2027 → Sep 2027 |
| October 1, 2024 | 87635 | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.