Buck Canyon

Named in 5 listed projects in ERCOT’s transmission project tracking workbook, in Borden County. First named in the release with data as of October 1, 2024.

Bordencounty as printed
345kV
WETTutility
5projects listed

Also printed as: Buck canyon

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Borden, TX: ERCOT queue, 17 active of 19 · SPP queue, 0 active of 1. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Ad Hoc TPIT: Build approximately 60-mile 345 kV double circuit from WETT's Buck Canyon to Nova Prime
ERCOT project 110622
WETT
Tier 1
Conceptual
Future tab
345 Dec 2029 Buck Canyon 345 kV to Nova Prime 345 kV
Borden / Kent County
Buck Canyon, Nova Prime
Ad Hoc TPIT: Build 345 kV double circuit from WETT's Buck Canyon to Oncor's White River station
ERCOT project 110683
WETT
Tier 1
Conceptual
Future tab
345 Dec 2029 Buck canyon 345 kV to Oncor's White River 345 kV station
Borden / Floyd County
Buck canyon, White River
Build approximately 94.5-mile 345 kV double circuit line from Buck Canyon to Pitchfork substation
ERCOT project 110851
WETT
Tier 1
Conceptual
Future tab
345 Dec 2029 Buck Canyon 345 kV to Pitchfork 345 kV
Borden / Dickens County
Buck Canyon, Pitchfork
WETT Buck Canyon 345 kV Station for Synchronous Condensers
ERCOT project 112691 · RPG 24RPG041
WETT
Tier 3
Under Construction
Future tab
345 Mar 2027 Long Draw to Buck Canyon
Borden County
Long Draw, Buck Canyon
WETT Buck Canyon Synchronous Condenser
ERCOT project 87633 · RPG 23RPG026
WETT
Tier 1
Under Construction
Future tab
345 Jul 2027 Buck Canyon to Buck Canyon
Borden County
Buck Canyon

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 2026112691First listedon the Future tab
July 13, 2026110622Projected in-service dateJul 2029 → Dec 2029
July 13, 2026110683Projected in-service dateSep 2028 → Dec 2029
July 13, 2026110851First listedon the Future tab
July 13, 2026110622First listedon the Future tab
July 13, 2026110683First listedon the Future tab
June 1, 202687633Status as reportedPlanned → Under Construction
June 1, 202587633Projected in-service dateMay 2027 → Jul 2027
February 1, 202587633Projected in-service dateOct 2027 → May 2027
October 1, 202487633First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.