Buck Canyon
Named in 5 listed projects in ERCOT’s transmission project tracking workbook, in Borden County. First named in the release with data as of October 1, 2024.
Also printed as: Buck canyon
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Borden, TX: ERCOT queue, 17 active of 19 · SPP queue, 0 active of 1. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Ad Hoc TPIT: Build approximately 60-mile 345 kV double circuit from WETT's Buck Canyon to Nova Prime ERCOT project 110622 |
WETT Tier 1 |
Conceptual Future tab |
345 | Dec 2029 | Buck Canyon 345 kV to Nova Prime 345 kV Borden / Kent County |
Buck Canyon, Nova Prime |
| Ad Hoc TPIT: Build 345 kV double circuit from WETT's Buck Canyon to Oncor's White River station ERCOT project 110683 |
WETT Tier 1 |
Conceptual Future tab |
345 | Dec 2029 | Buck canyon 345 kV to Oncor's White River 345 kV station Borden / Floyd County |
Buck canyon, White River |
| Build approximately 94.5-mile 345 kV double circuit line from Buck Canyon to Pitchfork substation ERCOT project 110851 |
WETT Tier 1 |
Conceptual Future tab |
345 | Dec 2029 | Buck Canyon 345 kV to Pitchfork 345 kV Borden / Dickens County |
Buck Canyon, Pitchfork |
| WETT Buck Canyon 345 kV Station for Synchronous Condensers ERCOT project 112691 · RPG 24RPG041 |
WETT Tier 3 |
Under Construction Future tab |
345 | Mar 2027 | Long Draw to Buck Canyon Borden County |
Long Draw, Buck Canyon |
| WETT Buck Canyon Synchronous Condenser ERCOT project 87633 · RPG 23RPG026 |
WETT Tier 1 |
Under Construction Future tab |
345 | Jul 2027 | Buck Canyon to Buck Canyon Borden County |
Buck Canyon |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 112691 | First listed | on the Future tab |
| July 13, 2026 | 110622 | Projected in-service date | Jul 2029 → Dec 2029 |
| July 13, 2026 | 110683 | Projected in-service date | Sep 2028 → Dec 2029 |
| July 13, 2026 | 110851 | First listed | on the Future tab |
| July 13, 2026 | 110622 | First listed | on the Future tab |
| July 13, 2026 | 110683 | First listed | on the Future tab |
| June 1, 2026 | 87633 | Status as reported | Planned → Under Construction |
| June 1, 2025 | 87633 | Projected in-service date | May 2027 → Jul 2027 |
| February 1, 2025 | 87633 | Projected in-service date | Oct 2027 → May 2027 |
| October 1, 2024 | 87633 | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.