Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Deaf Smith County. First named in the release with data as of June 1, 2026.

Deaf Smithcounty as printed
345kV
ONCORutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Deaf Smith, TX: ERCOT queue, 11 active of 11 · SPP queue, 0 active of 11. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Deaf Smith - Theory 345 kV Double-Circuit and Wallaby - AJ Swope 345 kV Line Cut-In
Construct Deaf Smith - Theory 345 kV Double-Circuit Line and Cut-In Wallaby - AJ Swope 345 kV Line into Deaf Smith 345 kV Switch
ERCOT project 104898 · utility no. R8899 · RPG 26RPG013
ONCOR
Tier 3
Planned
Future tab
345 Dec 2027 Deaf Smith to Theory
Deaf Smith County
Deaf Smith, Theory

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 2026104898First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.