Watermill Switch
Named in 7 listed projects in ERCOT’s transmission project tracking workbook, in Dallas County. First named in the release with data as of February 1, 2015.
Also printed as: Watermill
A HIFLD substation record has the same name and county: WATERMILL (DALLAS County). The names agree; that does not confirm they are the same facility.
Generation interconnection requests filed in Dallas, TX: ERCOT queue, 9 active of 11. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Watermill Switch – Stainback Switch 345kV Double-Circuit Line Upgrade Upgrade Watermill Switch – Stainback Switch 345kV Double-Circuit Line Upgrade ERCOT project 105332 · utility no. M4432 · RPG 25RPG004 |
ONCOR Tier 1 |
Planned Future tab |
345 | Dec 2027 | Watermill Switch to Stainback Switch Dallas County |
Watermill Switch, Stainback Switch |
| Watermill Switch – Wilson Switch 138 kV Double-Circuit Line Upgrade Watermill Switch – Wilson Switch 138 kV Double-Circuit Line ERCOT project 105334 · utility no. M4363 · RPG 25RPG004 |
ONCOR Tier 1 |
Planned Future tab |
138 | Dec 2027 | Watermill Switch to Wilson Switch Dallas County |
Watermill Switch, Wilson Switch |
| Watermill Switch - Tri Corner Switch 345 kV Double-Circuit Line Upgrade Watermill Switch - Tri Corner Switch 345 kV Double-Circuit Line ERCOT project 105757 · utility no. M4442 · RPG 25RPG004 · RTP 2024-NC11 |
ONCOR Tier 1 |
Planned Future tab |
345 | May 2032 | Watermill Switch to Tri Corner Switch Dallas County |
Watermill Switch, Tri Corner Switch |
| Loop Nine Switch - Watermill Switch 345 kV Line Upgrade Loop Nine Switch - Watermill Switch 345 kV Line ERCOT project 110389 · utility no. M4443 · RPG 25RPG042 · RTP 2024-NC16 |
ONCOR Tier 1 |
Planned Future tab |
345 | Jun 2029 | Loop Nine Switch to Watermill Switch Dallas County |
Loop Nine Switch, Watermill Switch |
| Seagoville-Watermill 138 kV Line Rebuild Seagoville-Watermill 138 kV Line ERCOT project 71178 · utility no. M4081 · RPG 23RPG033 |
ONCOR Tier 3 |
Planned Current-year planned tab |
138 | May 2026 | Seagoville to Watermill Dallas County |
Seagoville, Watermill |
| Watermill 345 kV Switch Rebuild the existing Watermill 345 kV Switch ERCOT project 71980 · utility no. M4012 · RPG 23RPG017 |
ONCOR Tier 3 |
Planned Completed tab |
345 | May 2025 actual 9999-01 |
Watermill Dallas County |
Watermill |
| Watermill to Reindeer 138 kV Line Upgrade Watermill to Reindeer 138 kV Line ERCOT project 92845 · utility no. M4430 |
ONCOR Tier 4 |
In-Service Completed tab |
138 | May 2026 actual 2026-05 |
Watermill Switch to Reindeer Dallas County |
Watermill Switch, Reindeer |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 92845 | Moved between tabs | Current-year planned → Completed |
| October 1, 2026 | 92845 | Status as reported | Planned → In-Service |
| July 13, 2026 | 110389 | First listed | on the Future tab |
| June 1, 2026 | 105332 | First listed | on the Future tab |
| June 1, 2026 | 105334 | First listed | on the Future tab |
| June 1, 2026 | 105757 | First listed | on the Future tab |
| February 1, 2026 | 71178 | Moved between tabs | Future → Current-year planned |
| February 1, 2026 | 92845 | Moved between tabs | Future → Current-year planned |
| October 1, 2025 | 71178 | Moved between tabs | Current-year planned → Future |
| October 1, 2025 | 71178 | Projected in-service date | Dec 2025 → May 2026 |
| June 1, 2025 | 71178 | Moved between tabs | Future → Current-year planned |
| June 1, 2025 | 71980 | Moved between tabs | Future → Completed |
| June 1, 2025 | 92845 | First listed | on the Future tab |
| June 1, 2024 | 71178 | Projected in-service date | May 2025 → Dec 2025 |
| June 1, 2024 | 71980 | Projected in-service date | Dec 2025 → May 2025 |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.