Substation Scout

Reforzar

Named in 1 listed project in ERCOT’s transmission project tracking workbook. First named in the release with data as of July 13, 2026.

—county as printed
345kV
STECutility
1projects listed

No HIFLD substation record has this name in this county.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
STEC Nueces Green Ammonia Load Interconnection Project
-Construct a new Farias 345-kV substation cutting in on the existing Reforzar to Lon Hill 345-kV transmission line -Loop in the new Farias onto the existing Lon Hill to Grissom 345-kV transmission line using single-circuit structures, with normal and emergency ratings of at least 1059 MVA and 1195 MVA, respectively, which will require a new right of way (ROW), approximately 5.9 miles; -Construct a…
ERCOT project 110443 · RPG 25RPG016
STEC
Tier 1
Conceptual
Future tab
345 May 2031 No terminals printed Farias, Reforzar, Lon Hill, Grissom, Chalcedony, Nueces, Bunsen

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 2026110443First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.