Grissom

Named in 3 listed projects in ERCOT’s transmission project tracking workbook. First named in the release with data as of October 1, 2021.

—county as printed
345kV
AEP TCC, STECutility
3projects listed

No HIFLD substation record has this name in this county.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Lon Hill to Grissom: Loop 345 kV into San Pedro
Loop in Lon Hill to Grissom 345 kV into 345 kV San Pedro Station
ERCOT project 110387 · RPG 25RPG016
AEP TCC
Tier 1
Conceptual
Future tab
345 Dec 2030 Lon Hill to Grissom Lon Hill, Grissom
STEC Nueces Green Ammonia Load Interconnection Project
-Construct a new Farias 345-kV substation cutting in on the existing Reforzar to Lon Hill 345-kV transmission line -Loop in the new Farias onto the existing Lon Hill to Grissom 345-kV transmission line using single-circuit structures, with normal and emergency ratings of at least 1059 MVA and 1195 MVA, respectively, which will require a new right of way (ROW), approximately 5.9 miles; -Construct a…
ERCOT project 110443 · RPG 25RPG016
STEC
Tier 1
Conceptual
Future tab
345 May 2031 No terminals printed Farias, Reforzar, Lon Hill, Grissom, Chalcedony, Nueces, Bunsen
STEC_110868_PalanganaLargeLoadProjectPhase4
STEC Nueces Green Ammonia Load Interconnection RPG Project: Install reactive support at 8704 GULCH7A 345-kV Substation Rebuild Angstrom - White Point 345-kV Line Rebuild Katoen - Lon Hill 345-kV line Rebuild Goddard - Katoen 345-kV line Rebuild Grissom - Nueces Green Ammonia 345-kV line Rebuild Paladio - Goddard 345-kV line Rebuild Paladio - Tango 345-kV line Rebuild Coleto - Raptor - Grissom 345-…
ERCOT project 110868
STEC
Tier 2
Conceptual
Future tab
345 May 2031 No terminals printed Substation Rebuild Angstrom, White Point, Katoen, Lon Hill, Goddard, Grissom, Nueces Green Ammonia, Paladio, Tango, Raptor

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 2026110868First listedon the Future tab
July 13, 2026110387First listedon the Future tab
July 13, 2026110443First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.