Eden
Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Concho County. First named in the release with data as of June 1, 2017.
Conchocounty as printed
69kV
AEP TNCutility
3projects listed
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Concho, TX: ERCOT queue, 10 active of 11. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Eden to North Brady: Rebuild 69 kV line Rehab Eden to North Brady 69 kV line ERCOT project 54892 · utility no. 1856 · RPG 22RPG009 |
AEP TNC Tier 4 |
Planned Future tab |
69 | Sep 2028 | Eden to North Brady Concho / McCulloch County |
Eden, North Brady |
| Ballinger to Eden 69 kV line: Rebuild taps Rebuild Taps on the Ballinger to Eden 69 kV line ERCOT project 6572 · utility no. 2814 |
AEP TNC Tier 4 |
Planned Future tab |
69 | Jun 2027 | Ballinger to Eden Runnels / Concho County |
Ballinger, Eden |
| Eden to Yellowjacket: Rebuild 69 kV Line Rehab the Eden to Yellowjacket 69 kV line ERCOT project 70710 · utility no. TA2021119 |
AEP TNC Tier 3 |
Planned Future tab |
69 | Nov 2027 | Eden to Yellowjacket Concho / Menard County |
Eden, Yellowjacket |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 54892 | Projected in-service date | Nov 2027 → Sep 2028 |
| October 1, 2026 | 6572 | Projected in-service date | Jul 2027 → Jun 2027 |
| February 1, 2026 | 54892 | Projected in-service date | Sep 2027 → Nov 2027 |
| February 1, 2026 | 6572 | Projected in-service date | Mar 2027 → Jul 2027 |
| October 1, 2025 | 6572 | Projected in-service date | Apr 2026 → Mar 2027 |
| February 1, 2025 | 54892 | Projected in-service date | Apr 2027 → Sep 2027 |
| February 1, 2025 | 6572 | Projected in-service date | Jan 2026 → Apr 2026 |
| October 1, 2024 | 6572 | Projected in-service date | Nov 2025 → Jan 2026 |
| June 1, 2024 | 70710 | Projected in-service date | Mar 2024 → Nov 2027 |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.
Site Scanner