Jordan
Named in 5 listed projects in ERCOT’s transmission project tracking workbook, in Chambers County. First named in the release with data as of February 1, 2015.
Expansion at an existing substation: new or expanded yard. The quoted wording describes a new or expanded yard, bus, bay or station at this substation. “Expand 138kV Jordan substation” — project 86022, as the utility reported it
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Chambers, TX: ERCOT queue, 2 active of 3 · MISO queue, 1 active of 3. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| This models upgrades required for a proposed load addition Install new 138kV CEHEsub Customer substation. Loop on Ckt. 48 to create new Ckt. 48 Jordan to CEHEsub to DUNCAN. ERCOT project 110092 |
CNP Tier 4 |
Conceptual Future tab |
138 | Apr 2028 | CEHEsub to Jordan/DUNCAN Chambers County |
CEHEsub, Jordan, DUNCAN |
| Install new TARGA 138kV customer substation as Ckt.86 Jordan to TARGA to CITIES. ERCOT project 76350 |
CNP Tier 4 |
In-Service Completed tab |
138 | Jan 2026 actual 2026-01 |
TARGA to Jordan/CITIES Chambers County |
TARGA, Jordan, CITIES |
| Jordan 138kV Substation Expansion for Coneflower Storage (23INR0425) Expand 138kV Jordan substation for Coneflower Storage generator interconnection (23INR0425) ERCOT project 86022 |
CNP Tier 4 |
Planned Future tab |
138 | Apr 2027 | Jordan to Coneflower Chambers County |
Jordan, Coneflower |
| Facility Ratings Methodology Phase 2 (FRM2) Upgrades Upgrade Ckt.97C Jordan to King to increase thermal limits as part of FRM2 upgrades. ERCOT project 99453H |
CNP Tier 4 |
Planned Current-year planned tab |
345 | Nov 2026 | Jordan to King Chambers / Harris County |
Jordan, King |
| Facility Ratings Methodology Phase 2 (FRM2) Upgrades Upgrade Ckt.97G Chambers to Jordan to increase thermal limits as part of FRM2 upgrades. ERCOT project 99453L |
CNP Tier 4 |
In-Service Completed tab |
345 | May 2026 actual 2026-03 |
Chambers to Jordan Harris / Chambers County |
Chambers, Jordan |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 99453H | Projected in-service date | Jul 2026 → Nov 2026 |
| July 13, 2026 | 99453H | Projected in-service date | Jun 2026 → Jul 2026 |
| July 13, 2026 | 110092 | First listed | on the Future tab |
| July 13, 2026 | 86022 | Moved between tabs | Current-year planned → Future |
| July 13, 2026 | 86022 | Projected in-service date | Dec 2026 → Apr 2027 |
| July 13, 2026 | 99453H | Projected in-service date | May 2026 → Jun 2026 |
| June 1, 2026 | 76350 | Moved between tabs | Current-year planned → Completed |
| June 1, 2026 | 76350 | Status as reported | Planned → In-Service |
| June 1, 2026 | 86022 | Projected in-service date | Oct 2026 → Dec 2026 |
| June 1, 2026 | 99453L | Moved between tabs | Current-year planned → Completed |
| June 1, 2026 | 99453L | Status as reported | Planned → In-Service |
| February 1, 2026 | 76350 | Moved between tabs | Future → Current-year planned |
| February 1, 2026 | 76350 | Projected in-service date | Jun 2026 → Jan 2026 |
| February 1, 2026 | 86022 | Moved between tabs | Future → Current-year planned |
| February 1, 2026 | 99453H | Moved between tabs | Future → Current-year planned |
| February 1, 2026 | 99453L | Moved between tabs | Future → Current-year planned |
| February 1, 2026 | 99453L | Projected in-service date | Oct 2029 → May 2026 |
| October 1, 2025 | 76350 | Moved between tabs | Current-year planned → Future |
| October 1, 2025 | 76350 | Projected in-service date | Dec 2025 → Jun 2026 |
| October 1, 2025 | 86022 | Projected in-service date | Feb 2027 → Oct 2026 |
| October 1, 2025 | 99453H | First listed | on the Future tab |
| October 1, 2025 | 99453L | First listed | on the Future tab |
| June 1, 2025 | 76350 | Moved between tabs | Future → Current-year planned |
| June 1, 2025 | 86022 | Projected in-service date | Oct 2026 → Feb 2027 |
| October 1, 2024 | 76350 | Projected in-service date | Jun 2025 → Dec 2025 |
| October 1, 2024 | 86022 | First listed | on the Future tab |
| June 1, 2024 | 76350 | Projected in-service date | May 2025 → Jun 2025 |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.