Villa Cavazos

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Cameron County. First named in the release with data as of October 1, 2023.

Cameroncounty as printed
138kV
AEP TCCutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Cameron, TX: ERCOT queue, 30 active of 32. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Villa Cavazos: Construct New 138 kV Terminal
Interconnect Eval BESS to the Villa Cavazos 138 kV station
ERCOT project 69471
AEP TCC
Tier 4
Planned
Future tab
138 Aug 2027 Villa Cavazos
Cameron County
Villa Cavazos

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
February 1, 202569471Projected in-service dateMar 2027 → Aug 2027
October 1, 202469471Projected in-service dateMay 2025 → Mar 2027

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.