Substation Scout

Union Carbide

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Cameron County. First named in the release with data as of October 1, 2023.

Cameroncounty as printed
138kV
AEP TCCutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Cameron, TX: ERCOT queue, 30 active of 32. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Union Carbide: Rebuild 138 kV Station
Rebuild Union Carbide as new AIS station Chalybe
ERCOT project 76082
AEP TCC
Tier 4
Planned
Future tab
138 Aug 2028
actual 9999-01
Union Carbide
Cameron County
Union Carbide

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202676082Projected in-service dateMay 2027 → Aug 2028
June 1, 202576082Projected in-service dateSep 2026 → May 2027
February 1, 202576082Projected in-service dateJun 2026 → Sep 2026

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.