Port South

Named in 0 listed projects in ERCOT’s transmission project tracking workbook, in Cameron County, plus 1 on its Cancelled tab. First named in the release with data as of June 1, 2019.

Cameroncounty as printed
138kV
STECutility
0projects listed

Projects cancelled. Every project naming Port South is on the Cancelled tab of ERCOT's workbook.

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Cameron, TX: ERCOT queue, 30 active of 32. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

No projects.

On the Cancelled tab

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Adds Annova and Port South Bus and lines
Adds Annova and Port South buses, lines to connect Annova to Port South, line from HWY 511 to Port South, and reconnects line from S Carbide to HWY 511 into Port South
ERCOT project 48854
STEC
Tier 4
Planned
Cancelled tab
138 Jun 2025 Annova LNG to Port South
Cameron County
Annova LNG, Port South

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202448854First listedon the Cancelled tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.