Substation Scout

Palo Alto 5965

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Cameron County. First named in the release with data as of May 12, 2023.

Cameroncounty as printed
138kV
BPUB/BROWNSVILLE PUButility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Cameron, TX: ERCOT queue, 30 active of 32. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
New transformer (T2) at BPUB Palo Alto Substation
Adding load (T2) on bus 5965 Palo Alto.
ERCOT project 73661
BPUB/BROWNSVILLE PUB
Tier 4
Planned
Future tab
138 Jun 2027 BPUB Palo Alto 5965
Cameron County
Palo Alto 5965

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 202673661Moved between tabsCurrent-year planned → Future
June 1, 202673661Projected in-service dateFeb 2026 → Jun 2027
February 1, 202673661Moved between tabsFuture → Current-year planned
June 1, 202573661Projected in-service dateApr 2025 → Feb 2026
June 1, 202473661Projected in-service dateMar 2024 → Apr 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.