Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Cameron County. First named in the release with data as of June 1, 2025.

Cameroncounty as printed
138kV
AEP TCCutility
1projects listed

Described as new. The quoted wording calls this substation new. “Ocelot: Construct New 138 kV Station” — project 76914 title, as the utility reported it

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Cameron, TX: ERCOT queue, 30 active of 32. Same county, not the same substation.

Location

Cameron County, TX

County only. A source prints the county; no point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.

Sources: ERCOT Transmission Project and Information Tracking (TPIT) workbook, projects 76914 (release 2026-10) · OpenStreetMap: Military Highway (way 513383712) and Palo Alto (way 513362299) substations, Brownsville (OSM base 2026-11-20). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Ocelot: Construct New 138 kV Station
Interconnect the Ocelot load to the new Ocelot 138 kV station on the Military Highway to Palo Alto 138 kV line
ERCOT project 76914
AEP TCC
Tier 4
Under Construction
Future tab
138 Mar 2027 Ocelot
Cameron County
Ocelot

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202676914Moved between tabsCurrent-year planned → Future
October 1, 202676914Projected in-service dateOct 2026 → Mar 2027
June 1, 202676914Projected in-service dateJun 2026 → Oct 2026
February 1, 202676914Moved between tabsFuture → Current-year planned
February 1, 202676914Status as reportedPlanned → Under Construction
February 1, 202676914Projected in-service dateFeb 2026 → Jun 2026
October 1, 202576914Moved between tabsCurrent-year planned → Future
October 1, 202576914Projected in-service dateDec 2025 → Feb 2026
June 1, 202576914Moved between tabsFuture → Current-year planned
February 1, 202576914Status as reportedConceptual → Planned
October 1, 202476914Moved between tabsCompleted → Future
October 1, 202476914Projected in-service dateJan 2024 → Dec 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.