Substation Scout

Candela

Named in 0 listed projects in ERCOT’s transmission project tracking workbook, in Cameron County, plus 1 on its Cancelled tab. First named in the release with data as of June 1, 2024.

Cameroncounty as printed
345kV
AEP TCCutility
0projects listed

Projects cancelled. Every project naming Candela is on the Cancelled tab of ERCOT's workbook.

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Cameron, TX: ERCOT queue, 30 active of 32. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

No projects.

On the Cancelled tab

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Candela: Construct New 345 kV Station
Interconnect the Zeta load to the new Candela 345 kV station
ERCOT project 81655
AEP TCC
Tier 4
Conceptual
Cancelled tab
345 Jun 2027 Candela
Cameron County
Candela

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 202581655Moved between tabsFuture → Cancelled
June 1, 202481655First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.