Reforzar
Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Brooks County, plus 1 on its Cancelled tab. First named in the release with data as of June 1, 2022.
Described as new. The quoted wording calls this substation new. “Reforzar: Construct New 345 kV Station” — project 66447 title, as the utility reported it
Reported complete. Project 66447 is on the Completed tab (actual in-service 2025-05), as the utility reported it. That indicates the substation may now be built; it is not a confirmation.
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Brooks, TX: ERCOT queue, 4 active of 4. Same county, not the same substation.
Location
Brooks County, TX
County only. A source prints the county; no point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.
Note: TPIT 66447 is on the Completed tab with status 'Under Construction' and ISD 2025-05, so the station may already be in service; the stage-2 project 76280 ('Reforzar: Build new 345 kV station - stage 2') is on the Cancelled tab. Not yet tagged in OpenStreetMap.
Sources: AEP Texas / ETT, Ajo - Reforzar Transmission Improvements Project fact sheet (final line route) (2024-11), p.2 map · PUCT Docket 55573, Order: Ajo-to-Reforzar double-circuit 345-kV transmission line in Brooks, Kenedy and Kleberg counties (2024), Order p.4, findings 13-14 · ERCOT TPIT, projects 66447, 67320, 67326, 76280 (release 39, 2026-10-01) · OpenStreetMap: Ajo Switching Station, SH 285, Lon Hill - North Edinburg 345 kV line (OSM base 2026-11-20). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Reforzar: Construct New 345 kV Station Construct a new 345 kV station on the Lon Hill to North Edinburg 345 kV line ERCOT project 66447 · utility no. TP2022035 · RPG 21RPG017 |
AEP TCC Tier 1 |
Under Construction Completed tab |
345 | May 2025 actual 2025-05 |
Reforzar Brooks County |
Reforzar |
| Cruce to Reforzar: Construct New 345 kV Double Circuit Line Construct a new 345 kV double circuit line from Cruce to Reforzar ERCOT project 67320 · utility no. TP2022033 · RPG 21RPG017 |
AEP TCC Tier 1 |
Under Construction Current-year planned tab |
345 | Oct 2026 | Cruce to Reforzar Jim Hogg / Brooks County |
Cruce, Reforzar |
| Ajo to Reforzar: Construct New 345 kV Double Circuit Line Construct a new 345 kV double circuit line from Ajo to Reforzar ERCOT project 67326 · utility no. TP2022030 · RPG 21RPG017 |
AEP TCC/ETT Tier 1 |
Under Construction Current-year planned tab |
345 | Sep 2026 | Ajo to Reforzar Kenedy / Brooks County |
Ajo, Reforzar |
On the Cancelled tab
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Reforzar: Build new 345 kV station - stage 2 Build new 345 kV station on the Lon Hill to North Edinburg 345 kV line ERCOT project 76280 · utility no. TP2022035 · RPG 21RPG017 |
AEP TCC Tier 1 |
Planned Cancelled tab |
345 | Jan 2026 | Reforzar Brooks County |
Reforzar |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 67320 | Projected in-service date | Sep 2026 → Oct 2026 |
| October 1, 2026 | 67326 | Projected in-service date | Aug 2026 → Sep 2026 |
| February 1, 2026 | 66447 | Status as reported | In-Service → Under Construction |
| February 1, 2026 | 67320 | Moved between tabs | Future → Current-year planned |
| February 1, 2026 | 67326 | Moved between tabs | Future → Current-year planned |
| October 1, 2025 | 66447 | Moved between tabs | Future → Completed |
| October 1, 2025 | 66447 | Status as reported | Under Construction → In-Service |
| October 1, 2025 | 66447 | Projected in-service date | Nov 2026 → May 2025 |
| October 1, 2025 | 67320 | Status as reported | Planned → Under Construction |
| October 1, 2025 | 67326 | Status as reported | Planned → Under Construction |
| October 1, 2025 | 67326 | Projected in-service date | Jun 2026 → Aug 2026 |
| June 1, 2025 | 66447 | Status as reported | Planned → Under Construction |
| February 1, 2025 | 67320 | Projected in-service date | Jan 2027 → Sep 2026 |
| February 1, 2025 | 67326 | Projected in-service date | Nov 2026 → Jun 2026 |
| October 1, 2024 | 67320 | Projected in-service date | Nov 2026 → Jan 2027 |
| June 1, 2024 | 76280 | Moved between tabs | Future → Cancelled |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.