Reforzar

Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Brooks County, plus 1 on its Cancelled tab. First named in the release with data as of June 1, 2022.

Brookscounty as printed
345kV
AEP TCC, AEP TCC/ETTutility
3projects listed

Described as new. The quoted wording calls this substation new. “Reforzar: Construct New 345 kV Station” — project 66447 title, as the utility reported it

Reported complete. Project 66447 is on the Completed tab (actual in-service 2025-05), as the utility reported it. That indicates the substation may now be built; it is not a confirmation.

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Brooks, TX: ERCOT queue, 4 active of 4. Same county, not the same substation.

Location

Brooks County, TX

County only. A source prints the county; no point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.

Note: TPIT 66447 is on the Completed tab with status 'Under Construction' and ISD 2025-05, so the station may already be in service; the stage-2 project 76280 ('Reforzar: Build new 345 kV station - stage 2') is on the Cancelled tab. Not yet tagged in OpenStreetMap.

Sources: AEP Texas / ETT, Ajo - Reforzar Transmission Improvements Project fact sheet (final line route) (2024-11), p.2 map · PUCT Docket 55573, Order: Ajo-to-Reforzar double-circuit 345-kV transmission line in Brooks, Kenedy and Kleberg counties (2024), Order p.4, findings 13-14 · ERCOT TPIT, projects 66447, 67320, 67326, 76280 (release 39, 2026-10-01) · OpenStreetMap: Ajo Switching Station, SH 285, Lon Hill - North Edinburg 345 kV line (OSM base 2026-11-20). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Reforzar: Construct New 345 kV Station
Construct a new 345 kV station on the Lon Hill to North Edinburg 345 kV line
ERCOT project 66447 · utility no. TP2022035 · RPG 21RPG017
AEP TCC
Tier 1
Under Construction
Completed tab
345 May 2025
actual 2025-05
Reforzar
Brooks County
Reforzar
Cruce to Reforzar: Construct New 345 kV Double Circuit Line
Construct a new 345 kV double circuit line from Cruce to Reforzar
ERCOT project 67320 · utility no. TP2022033 · RPG 21RPG017
AEP TCC
Tier 1
Under Construction
Current-year planned tab
345 Oct 2026 Cruce to Reforzar
Jim Hogg / Brooks County
Cruce, Reforzar
Ajo to Reforzar: Construct New 345 kV Double Circuit Line
Construct a new 345 kV double circuit line from Ajo to Reforzar
ERCOT project 67326 · utility no. TP2022030 · RPG 21RPG017
AEP TCC/ETT
Tier 1
Under Construction
Current-year planned tab
345 Sep 2026 Ajo to Reforzar
Kenedy / Brooks County
Ajo, Reforzar

On the Cancelled tab

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Reforzar: Build new 345 kV station - stage 2
Build new 345 kV station on the Lon Hill to North Edinburg 345 kV line
ERCOT project 76280 · utility no. TP2022035 · RPG 21RPG017
AEP TCC
Tier 1
Planned
Cancelled tab
345 Jan 2026 Reforzar
Brooks County
Reforzar

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202667320Projected in-service dateSep 2026 → Oct 2026
October 1, 202667326Projected in-service dateAug 2026 → Sep 2026
February 1, 202666447Status as reportedIn-Service → Under Construction
February 1, 202667320Moved between tabsFuture → Current-year planned
February 1, 202667326Moved between tabsFuture → Current-year planned
October 1, 202566447Moved between tabsFuture → Completed
October 1, 202566447Status as reportedUnder Construction → In-Service
October 1, 202566447Projected in-service dateNov 2026 → May 2025
October 1, 202567320Status as reportedPlanned → Under Construction
October 1, 202567326Status as reportedPlanned → Under Construction
October 1, 202567326Projected in-service dateJun 2026 → Aug 2026
June 1, 202566447Status as reportedPlanned → Under Construction
February 1, 202567320Projected in-service dateJan 2027 → Sep 2026
February 1, 202567326Projected in-service dateNov 2026 → Jun 2026
October 1, 202467320Projected in-service dateNov 2026 → Jan 2027
June 1, 202476280Moved between tabsFuture → Cancelled

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.