Weinbrenner
Named in 4 listed projects in ERCOT’s transmission project tracking workbook, in Brazoria County. First named in the release with data as of February 1, 2024.
Expansion at an existing substation: new or expanded yard. The quoted wording describes a new or expanded yard, bus, bay or station at this substation. “Expand 138kV Weinbrenner substation” — project 102980, as the utility reported it
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Brazoria, TX: ERCOT queue, 54 active of 63. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Expand 138kV Weinbrenner substation for LIATRI (LIA)/Liatris Flexible Gas - 26INR0408. Install one new generator lead from Weinbrenner to LIATRI/Liatris Flexible Gas ERCOT project 102980 |
CNP Tier 4 |
Planned Future tab |
138 | Nov 2028 | Weinbrenner Brazoria County |
Weinbrenner |
| Weinbrenner (WEI) 138kV CEHE Station for LONGPO (LNP) / Long Point Solar 19INR0042 Loop new CEHE 138kV substation Weinbrenner (WEI) into Ckt.02J Burke to Eagle Nest to create new Ckt.02 Burke to Weinbrenner to Eagle Nest. ERCOT project 78480A |
CNP Tier 4 |
In-Service Completed tab |
138 | Nov 2025 actual 2025-12 |
Weinbrenner to Burke/ Eagle Nest Brazoria County |
Weinbrenner, Burke, Eagle Nest |
| Weinbrenner (WEI) 138kV CEHE Station for LONGPO (LNP) / Long Point Solar 19INR0042 Install one generator lead from CEHE 138kV substation Weinbrenner (WEI) to LONGPO (LNP) / Long Point Solar (19INR0042) ERCOT project 78480B |
CNP Tier 4 |
In-Service Completed tab |
138 | Nov 2025 actual 2025-12 |
Weinbrenner to LONGPO Brazoria County |
Weinbrenner, LONGPO |
| Weinbrenner 138kV Substation Expansion for SWITCH (SWG)/Elio BESS (25INR0103) Expand 138kV Weinbrenner substation for SWITCH (SWG)/Elio BESS (25INR0103). Install one new generator lead from Weinbrenner to SWITCH/Elio BESS ERCOT project 89924 |
CNP Tier 4 |
Planned Future tab |
138 | May 2027 | Weinbrenner Brazoria County |
Weinbrenner |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| July 13, 2026 | 102980 | Projected in-service date | Sep 2027 → Nov 2028 |
| June 1, 2026 | 102980 | First listed | on the Future tab |
| February 1, 2026 | 78480A | Moved between tabs | Current-year planned → Completed |
| February 1, 2026 | 78480A | Status as reported | Planned → In-Service |
| February 1, 2026 | 78480B | Moved between tabs | Current-year planned → Completed |
| February 1, 2026 | 78480B | Status as reported | Planned → In-Service |
| October 1, 2025 | 78480A | Projected in-service date | Oct 2025 → Nov 2025 |
| October 1, 2025 | 78480B | Moved between tabs | Future → Current-year planned |
| October 1, 2025 | 78480B | Projected in-service date | Apr 2026 → Nov 2025 |
| June 1, 2025 | 78480A | Moved between tabs | Future → Current-year planned |
| June 1, 2025 | 78480B | Projected in-service date | Oct 2025 → Apr 2026 |
| February 1, 2025 | 89924 | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.