Franklins Camp

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Brazoria County. First named in the release with data as of June 1, 2015.

Brazoriacounty as printed
138kV
CNPutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Brazoria, TX: ERCOT queue, 54 active of 63. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
New 138kV Waterfowl substation
Install new CEHE-owned 138kV Waterfowl (WTR) substation. Remove existing Seaway Switchrack. Reconfigure existing Ckt.02F to create new Ckt.02L Waterfowl to Franklins Camp.
ERCOT project 64581D · RPG 21RPG009
CNP
Tier 3
In-Service
Completed tab
138 May 2026
actual 2026-05
Waterfowl to Franklins Camp
Brazoria County
Waterfowl, Franklins Camp

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 202664581DMoved between tabsCurrent-year planned → Completed
June 1, 202664581DStatus as reportedPlanned → In-Service
June 1, 202664581DProjected in-service dateApr 2026 → May 2026
February 1, 202664581DMoved between tabsFuture → Current-year planned
October 1, 202564581DProjected in-service dateJan 2026 → Apr 2026
February 1, 202564581DProjected in-service dateOct 2025 → Jan 2026

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.