Big Creek

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Brazoria County. First named in the release with data as of October 1, 2022.

Brazoriacounty as printed
138kV
CNPutility
1projects listed

No HIFLD substation record has this name in this county (a record of the same name exists in another county).

Generation interconnection requests filed in Brazoria, TX: ERCOT queue, 54 active of 63. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
West Columbia to Damon and Needville to Big Creek Ckt.89A Upgrades
Rebuild/reconductor Needville to Big Creek Ckt.89 as a Hardening upgrade.
ERCOT project 78461B · RPG 23RPG021
CNP
Tier 4
Planned
Future tab
138 Jan 2027 Needville to Big Creek
Brazoria County
Needville, Big Creek

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 202678461BMoved between tabsCurrent-year planned → Future
July 13, 202678461BProjected in-service dateDec 2026 → Jan 2027
February 1, 202678461BMoved between tabsFuture → Current-year planned

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.