S-0978 QTS Ingram Rd
Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Bexar County. First named in the release with data as of June 1, 2026.
Bexarcounty as printed
138kV
CPS/NOutility
1projects listed
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Bexar, TX: ERCOT queue, 22 active of 23. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| New Ingram Rd 138kV Substation Install a new 138kV transmission loop in conjunction with the S-0978 QTS Ingram Rd Substation project. The substation will be looped into the Potranco to TCC/Crossroads transmission line and connected to (2) 138kV line terminals. ERCOT project 72268 · utility no. S-0978 |
CPS/NO Tier 4 |
Under Construction Current-year planned tab |
138 | Dec 2026 | 5241 to 5102, 5346 Bexar County |
Ingram Rd, S-0978 QTS Ingram Rd |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 72268 | Status as reported | Planned → Under Construction |
| June 1, 2026 | 72268 | Projected in-service date | Oct 2026 → Dec 2026 |
| February 1, 2026 | 72268 | Moved between tabs | Future → Current-year planned |
| October 1, 2025 | 72268 | Projected in-service date | Feb 2026 → Oct 2026 |
| June 1, 2025 | 72268 | Projected in-service date | Dec 2025 → Feb 2026 |
| June 1, 2024 | 72268 | Projected in-service date | May 2025 → Dec 2025 |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.