Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Bexar County. First named in the release with data as of May 12, 2023.

Bexarcounty as printed
138kV
CPS/NOutility
1projects listed

Described as new. The quoted wording calls this substation new. “New Ingram Rd 138kV Substation” — project 72268 title, as the utility reported it

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Bexar, TX: ERCOT queue, 22 active of 23. Same county, not the same substation.

Location

Bexar County, TX

County only. A source prints the county; no point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.

Note: The CPS address (1495 Ingram Rd., San Antonio, TX 78251) did not geocode to a point (Census geocoder: no match; Nominatim returns only the street), and the brochure's location map is an unscaled street sketch (a 'Future Substation Site' outline north of Potranco Rd.) that could not be anchored reliably, so no point is given. The CPS page's Google Maps link points at the street 'Ingram Rd', not at the site. OSM's 'Potranco Substation' (CPS, way 509607715) ~0.4 km from the Ingram/Potranco intersection is an existing station, not this one.

Sources: CPS Energy, Ingram Rd. Substation & Transmission Project brochure (2023-09-21), p.2 text and Project Location Map · CPS Energy, Ingram Road Substation and Transmission Project page (n/a) · ERCOT TPIT, project 72268 (release 39, 2026-10-01). Researched by Substation Scout; checked November 21, 2026.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
New Ingram Rd 138kV Substation
Install a new 138kV transmission loop in conjunction with the S-0978 QTS Ingram Rd Substation project. The substation will be looped into the Potranco to TCC/Crossroads transmission line and connected to (2) 138kV line terminals.
ERCOT project 72268 · utility no. S-0978
CPS/NO
Tier 4
Under Construction
Current-year planned tab
138 Dec 2026 5241 to 5102, 5346
Bexar County
Ingram Rd, S-0978 QTS Ingram Rd

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202672268Status as reportedPlanned → Under Construction
June 1, 202672268Projected in-service dateOct 2026 → Dec 2026
February 1, 202672268Moved between tabsFuture → Current-year planned
October 1, 202572268Projected in-service dateFeb 2026 → Oct 2026
June 1, 202572268Projected in-service dateDec 2025 → Feb 2026
June 1, 202472268Projected in-service dateMay 2025 → Dec 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.