Helotes

Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Bexar County. First named in the release with data as of February 1, 2015.

Bexarcounty as printed
138, 345kV
CPS/NOutility
3projects listed

Described as new. The quoted wording calls this substation new. “new Helotes 345kV substation” — project 110263 title, as the utility reported it

A HIFLD substation record has the same name and county: HELOTES (BEXAR County). The names agree; that does not confirm they are the same facility.

Generation interconnection requests filed in Bexar, TX: ERCOT queue, 22 active of 23. Same county, not the same substation.

Location

29.5482, -98.6819 · Bexar County, TX · view on a map

OpenStreetMap, corroborated. An OpenStreetMap feature carries this exact name, and a cited source agrees. Accurate to about ±200 m, as estimated by the research. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.

How it was located: OSM way 97043744 'Helotes Substation' (operator CPS Energy, voltage 138000), centroid. ERCOT's recommended Option 3A says the new 345-kV yard is a conversion of 'the existing Helotes 138-kV substation', so the existing station's point is the station itself, not a neighbour. Corroborated by OSM 345 kV line way 91982757 passing 0.11 km from the station, consistent with looping 'the existing Hill Country to Cagnon 345-kV transmission line into the new Helotes 345-kV substation'. The new 345-kV yard may extend beyond the existing fence; +/- ~200 m.

Note: Not a new site: ERCOT describes a conversion of the existing Helotes 138-kV substation into a 345/138-kV switching substation (closer to an expansion with a new voltage level than a new substation). TPIT 110263 status 'Under Construction', ISD 2028-05; ERCOT's board report gives an expected ISD of October 2031 for the combined project.

County: the Census county at this point.

Sources: ERCOT Board item 5.1: CPS Combined Reactive Power Planning Project & Helotes 345/138-kV Switching Station and Autotransformer Addition at Eastside Switching Station (25RPG013/25RPG017) (2026-05-22), pp.1-3 · OpenStreetMap: Helotes Substation; 345 kV line way 91982757 (OSM base 2026-11-20) · ERCOT TPIT, projects 110263, 109956, 100687 (release 39, 2026-10-01). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Install a 50MVAr Capacitor Bank at Helotes Substation
ERCOT project 100687 · utility no. S-1075
CPS/NO
Tier 4
Planned
Future tab
138 Jun 2029 5200
Bexar County
Helotes
Rebuild Anderson to Helotes 138kV Transmission Line
ERCOT project 109956 · utility no. T-XXXX · RPG 25RPG013 and 25RPG017
CPS/NO
Tier 1
Planned
Future tab
138 Jan 2032 5003 to 5200
Bexar County
Anderson, Helotes
A new Helotes 345kV substation will be constructed
ERCOT project 110263 · utility no. T-0410 · RPG 25RPG013 and 25RPG017
CPS/NO
Tier 1
Under Construction
Future tab
345 May 2028 5201 to 5056, 5211, 5200
Bexar County
Helotes

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 2026110263Status as reportedPlanned → Under Construction
July 13, 2026109956Projected in-service dateDec 2029 → Jan 2032
July 13, 2026109956First listedon the Future tab
July 13, 2026110263First listedon the Future tab
October 1, 2025100687First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.