Anderson
Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Bexar County. First named in the release with data as of February 1, 2015.
A HIFLD substation record has the same name and county: ANDERSON (BEXAR County). The names agree; that does not confirm they are the same facility.
Generation interconnection requests filed in Bexar, TX: ERCOT queue, 22 active of 23. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Install a 50MVAr Capacitor Bank at Anderson Substation ERCOT project 100647 · utility no. S-1043 · RPG 24RPG004 |
CPS/NO Tier 2 |
Planned Future tab |
138 | Dec 2028 | 5003 Bexar County |
Anderson |
| Rebuild Anderson to Helotes 138kV Transmission Line ERCOT project 109956 · utility no. T-XXXX · RPG 25RPG013 and 25RPG017 |
CPS/NO Tier 1 |
Planned Future tab |
138 | Jan 2032 | 5003 to 5200 Bexar County |
Anderson, Helotes |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| July 13, 2026 | 100647 | Projected in-service date | Jun 2028 → Dec 2028 |
| July 13, 2026 | 109956 | Projected in-service date | Dec 2029 → Jan 2032 |
| July 13, 2026 | 109956 | First listed | on the Future tab |
| October 1, 2025 | 100647 | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.