Substation Scout

Thunder Ridge

Named in 3 PJM planning documents for 1 project, from November 14, 2025 to October 6, 2026.

Newdescribed as
EKPCzone
69 kVkV as printed
3mentions

Described as new: “Build new 69 kV switching station called Thunder Ridge” — source, page 7

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Skaggs, KY
EKPC-2025-005 · s4026.1-s4026.4
Engineering $14.13 M 12/30/2031 Not printed 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 12/31/2028 → 12/30/2031 2025-11-14 2026-10-06
Substations named DEWEY DAM; JENNY WILEY; MAGOFFIN CO; ROWAN COUNTY; SKAGGS; THELMA; THUNDER RIDGE → AEP DEWEY DAM; AEP THELMA; DEWEY; JENNY WILEY; MAGOFFIN CO; SKAGGS; THELMA; THUNDER RIDGE 2026-10-06 Not reported
Substations named AEP THELMA; ROWAN COUNTY; SKAGGS; THELMA → AEP THELMA; DEWEY; DEWEY DAM; JENNY WILEY; ROWAN COUNTY; SKAGGS; THELMA; THUNDER RIDGE 2025-10-17 2025-11-14
Substations named AEP THELMA; DEWEY; DEWEY DAM; JENNY WILEY; ROWAN COUNTY; SKAGGS; THELMA; THUNDER RIDGE → DEWEY DAM; JENNY WILEY; MAGOFFIN CO; ROWAN COUNTY; SKAGGS; THELMA; THUNDER RIDGE 2025-11-14 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - EKPC Local Plan Submission of Supplemental Projects for 2026 p. 7
Skaggs, KY “Build new 69 kV switching station called Thunder Ridge”
69 kV
2026-10-01* SRRTEP Western
EKPC local plan submission of the supplemental projects for 2026 RTEP p. 7
Skaggs, KY “Build new 69 kV switching station called Thunder Ridge”
69 kV
2025-11-14 SRRTEP Western
Item 07 - EKPC Supplemental Projects p. 4
Skaggs, KY “Build new 69 kV switching station called Thunder Ridge”
69 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.