Clay Village distribution substation

Named in 1 PJM planning document for 1 project, on December 13, 2024.

Existingdescribed as
EKPCzone
—kV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Clay Village, KY
EKPC-2023-009
Engineering $1.265 M 06/01/2026 12 MW 2024-12-13
SRRTEP Western

Every mention

DateDocumentProjectWhat the document says about it
2024-12-13 SRRTEP Western
Item 13 - EKPC Supplemental Projects p. 5
Clay Village, KY “currently served from the Clay Village distribution substation”