Substation Scout

SPP request GEN-2016-014

SPP queue ID GEN-2016-014

Queue request GEN-2016-014 was listed in the SPP interconnection queue at the end of 2025 as a 10 MW gas project in Jasper County, MO, according to Berkeley Lab’s queue data file. The filing names LaRussell Energy Center as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of April 30, 2020.

Queue IDGEN-2016-014
Project nameNot reported
Status (as published)Operational
SubstationLaRussell Energy Center
Point of interconnectionLaRussell Energy Center 161kV
CountyJasper
StateMO
Voltage161 kV
Capacity10 MW
Resource (as published)Gas
Resource categoryGas (normalized for filtering)
Proposed online date2020-04-30
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

LaRussell Energy Center substation: 5 requests in the SPP queue, 5 active totaling 269.4 MW.

Queue IDProjectMWResourceStatus
GEN-2017-060Not reported149.4WindOperational
GEN-2001-030Not reported50GasOperational
GEN-2001-040Not reported50GasOperational
GEN-2016-013Not reported10GasOperational

Jasper, MO: 22 requests in the SPP queue, 9 active totaling 784 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityEDE
ClusterDISIS-2016-001-3; 03 CENTRAL
Interconnection serviceERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)IA FULLY EXECUTED/COMMERCIAL OPERATION
Queue date2016-03-29
Operational date2020-04-30

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner