Queue request GEN-2006-018 was listed in the SPP interconnection queue at the end of 2025 as a 168.1 MW gas project in Hale County, TX, according to Berkeley Lab’s queue data file. The filing names TUCO as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of March 22, 2011.

Queue IDGEN-2006-018
Project nameNot reported
Status (as published)Operational
SubstationTUCO
Point of interconnectionTUCO 230kV
CountyHale
StateTX
Voltage230 kV
Capacity168.1 MW
Resource (as published)Gas
Resource categoryGas (normalized for filtering)
Proposed online date2011-03-22
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

TUCO substation: 11 requests in the SPP queue, 5 active totaling 1,057.1 MW.

Queue IDProjectMWResourceStatus
GEN-2012-020Not reported478WindOperational
GEN-2012-037Not reported203GasOperational
GEN-2013-016Not reported203GasOperational
GEN-2015-041Not reported5GasOperational
GEN-2015-068Not reported300WindWithdrawn
GEN-2010-034Not reported261WindWithdrawn
GEN-2010-033Not reported230WindWithdrawn
GEN-2010-032Not reported216WindWithdrawn
GEN-2017-059Not reported90SolarWithdrawn
GEN-2010-046Not reported56GasWithdrawn

Hale, TX: 22 requests in the SPP queue, 8 active totaling 1,977.1 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilitySPS
ClusterICS-2008-001 Prior Queued; 05 SOUTHWEST
Interconnection serviceERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)IA FULLY EXECUTED/COMMERCIAL OPERATION
Queue date2010-06-01
Operational date2011-03-22

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first