Ward, ND interconnection queue
4 active projects totaling 407.7 MW in the SPP queue, plus 3 with terminal status (shown grayed).
4active projects
407.7active MW
7total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| GEN-2024-327 | Not reported | 115 | 200 | Battery | Active |
| GEN-2017-214 | Not reported | 230 | 100 | Wind | Active |
| GEN-2017-215 | Not reported | 230 | 100 | Wind | Active |
| GEN-2017-216 | Not reported | 230 | 100 | Wind | Withdrawn |
| GEN-2017-235 | Not reported | 230 | 50 | Wind | Withdrawn |
| GEN-2017-236 | Not reported | 230 | 50 | Wind | Withdrawn |
| GEN-2025-GR5 | Not reported | n/r | 7.7 | Wind | Active |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.