Substation Scout

SPP request GEN-2025-GR5

SPP queue ID GEN-2025-GR5

Queue request GEN-2025-GR5 was listed in the SPP interconnection queue at the end of 2025 as a 7.7 MW wind project in Ward County, ND, according to Berkeley Lab’s queue data file. The filing names Nelson Tap as its point of interconnection. Its status as of December 31, 2025 was “Active”.

Queue IDGEN-2025-GR5
Project nameNot reported
Status (as published)Active
SubstationNelson Tap
Point of interconnectionNelson Tap
CountyWard
StateND
VoltageNot reported
Capacity7.7 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online dateNot reported
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Ward, ND: 7 requests in the SPP queue, 4 active totaling 407.7 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityWAPA
ClusterReplacement; 01 NORTH
Interconnection serviceNRIS/ERIS
Project typeReplacement
Study phase (standardized by Berkeley Lab)In Progress (unknown study)
Study phase (as the queue printed it)None
Queue date2025-10-06

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.