7 active projects totaling 1,173.9 MW in the SPP queue, plus 10 with terminal status (shown grayed).
7active projects
1,173.9active MW
17total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| GEN-2006-037 | Not reported | n/r | 900 | Coal | Withdrawn |
| GEN-2021-071 | Not reported | 345 | 403.2 | Wind | Withdrawn |
| GEN-2008-111 | Not reported | n/r | 400 | Wind | Withdrawn |
| GEN-2015-047 | Not reported | 345 | 300 | Wind | Operational |
| GEN-2021-018 | Not reported | 345 | 231 | Solar | Active |
| GEN-2025-SR8 | Not reported | 345 | 220 | Battery | Active |
| GEN-2015-030 | Not reported | 345 | 200.1 | Wind | Withdrawn |
| GEN-2016-101 | Not reported | 345 | 195 | Wind | Withdrawn |
| GEN-2015-067 | Not reported | 138 | 150 | Solar | Withdrawn |
| GEN-2024-056 | Not reported | 138 | 120 | Solar | Active |
| GEN-2025-SR12 | Not reported | n/r | 116 | Battery | Active |
| GEN-2025-SR11 | Not reported | n/r | 112 | Battery | Active |
| GEN-2008-104 | Not reported | n/r | 100 | Wind | Withdrawn |
| GEN-2008-105 | Not reported | n/r | 100 | Wind | Withdrawn |
| GEN-2016-100 | Not reported | 345 | 100 | Wind | Withdrawn |
| GEN-2021-019 | Not reported | 345 | 74.9 | Battery | Active |
| GEN-2005-019 | Not reported | n/r | 32 | Gas | Withdrawn |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.