6 active projects totaling 2,475 MW in the SPP queue, plus 8 with terminal status (shown grayed).

6active projects
2,475active MW
14total filed
Queue IDProjectkVMWResourceStatus
ERAS-2025-011 Not reported 345 750 Gas Active
ERAS-2025-012 Not reported 345 750 Gas Active
GEN-2021-072 Not reported 345 600 Solar Withdrawn
GEN-2021-094 Not reported 345 446.5 Gas Withdrawn
GEN-2021-095 Not reported 345 446.5 Gas Withdrawn
GEN-2024-141 Not reported 230 424 Wind Active
GEN-2016-130 Not reported 345 202 Wind Operational
GEN-2016-108 Not reported 345 200 Wind Withdrawn
GEN-2024-191 Not reported 345 199 Battery Withdrawn
GEN-2024-192 Not reported 345 199 Battery Withdrawn
GEN-2024-284 Not reported 345 199 Solar Active
GEN-2019-037 Not reported 345 150 Solar Active
GEN-2024-174 Not reported 115 130 Battery Withdrawn
GEN-2021-100 Not reported 345 50 Battery Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first