Substation Scout

Lea, NM interconnection queue

22 active projects totaling 4,552 MW in the SPP queue, plus 56 with terminal status (shown grayed).

22active projects
4,552active MW
78total filed
Queue IDProjectkVMWResourceStatus
GEN-2023-081 Not reported 345 625 Hybrid Withdrawn
GEN-2006-026 Not reported 230 604 Gas Operational
GEN-2008-132 Not reported n/r 604 Gas Withdrawn
GEN-2007-054 Not reported n/r 550 Gas Withdrawn
GEN-2006-023 Not reported n/r 549 Gas Withdrawn
GEN-2024-073 Not reported 345 500 Hybrid Active
GEN-2024-124 Not reported 345 420 Hybrid Active
ERAS-2025-020 Not reported 345 400 Hybrid Active
GEN-2023-236 Not reported 345 400 Solar Withdrawn
GEN-2018-118 Not reported 345 305 Solar Withdrawn
GEN-2019-031 Not reported 230 302.6 Solar Withdrawn
GEN-2014-008 Not reported 345 300 Wind Withdrawn
GEN-2016-084 Not reported n/r 300 Wind Withdrawn
GEN-2023-201 Not reported 345 300 Hybrid Withdrawn
GEN-2023-203 Not reported 230 300 Hybrid Withdrawn
GEN-2024-278 Not reported 345 264.3 Hybrid Active
GEN-2016-169 Not reported 345 260 Solar Withdrawn
GEN-2007-055 Not reported n/r 250 Wind Withdrawn
GEN-2020-059 Not reported 345 250 Hybrid Withdrawn
GEN-2022-029 Not reported 345 250 Hybrid Withdrawn
GEN-2022-030 Not reported 345 250 Hybrid Withdrawn
GEN-2024-262 Not reported 345 250 Hybrid Withdrawn
GEN-2024-263 Not reported 345 250 Hybrid Withdrawn
GEN-2024-281 Not reported 115 250 Hybrid Active
GEN-2024-371 Not reported 115 250 Battery Active
GEN-2017-104 Not reported 230 240 Solar Withdrawn
GEN-2018-078 Not reported n/r 240 Wind Withdrawn
GEN-2019-025 Not reported 230 240 Hybrid Withdrawn
GEN-2023-001 Not reported n/r 230 Solar Withdrawn
GEN-2008-050 Not reported n/r 201 Wind Withdrawn
GEN-2012-019 Not reported 345 200 Wind Withdrawn
GEN-2024-365 Not reported 345 200 Wind Active
GEN-2024-366 Not reported 345 200 Wind Active
GEN-2024-264 Not reported 230 199 Hybrid Withdrawn
GEN-2024-351 Not reported 115 199 Hybrid Active
GEN-2024-GR3 Not reported 230 196 Solar Active
ERAS-2025-014 Not reported 345 159.5 Gas Active
GEN-2024-265 Not reported 115 155 Hybrid Active
GEN-2014-030 Not reported 345 150 Solar Withdrawn
GEN-2019-026 Not reported 230 150 Battery Withdrawn
GEN-2022-109 Not reported 345 150 Solar Withdrawn
GEN-2022-135 Not reported 115 150 Battery Withdrawn
GEN-2024-008 Not reported 115 150 Solar Withdrawn
GEN-2024-009 Not reported 230 150 Solar Withdrawn
GEN-2024-010 Not reported 230 150 Solar Withdrawn
GEN-2024-011 Not reported 115 150 Solar Withdrawn
GEN-2024-261 Not reported 115 150 Hybrid Active
GEN-2024-306 Not reported 115 150 Battery Active
GEN-2009-039 Not reported n/r 147 Wind Withdrawn
GEN-2015-079 Not reported 230 129.2 Solar Withdrawn
GEN-2015-080 Not reported 230 129.2 Solar Withdrawn
GEN-2014-070 Not reported 230 113 Solar Withdrawn
GEN-2017-145 Not reported 115 110.3 Solar Withdrawn
GEN-2016-121 Not reported 115 110 Solar Active
GEN-2021-062 Not reported 115 110 Solar Withdrawn
GEN-2014-024 Not reported 230 100 Solar Withdrawn
GEN-2016-080 Not reported n/r 100 Solar Withdrawn
GEN-2021-080 Not reported 69 100 Hybrid Withdrawn
GEN-2009-038 Not reported 230 99 Wind Withdrawn
GEN-2014-065 Not reported 115 99 Solar Withdrawn
GEN-2017-093 Not reported 115 99 Solar Withdrawn
GEN-2016-085 Not reported 115 80 Solar Withdrawn
GEN-2021-082 Not reported 69 80 Hybrid Withdrawn
GEN-2018-004 Not reported 115 75 Solar Active
GEN-2025-SR29 Not reported 115 75 Battery Active
GEN-2021-020 Not reported 345 74 Solar Withdrawn
GEN-2015-099 Not reported 115 73.3 Solar Withdrawn
GEN-2023-GR4 Not reported 115 72 Solar Active
GEN-2018-052 Not reported 115 70 Battery Active
GEN-2016-171 Not reported 230 64 Solar Withdrawn
GEN-2019-004 Not reported 230 56 Gas Withdrawn
GEN-2021-081 Not reported 69 55 Hybrid Withdrawn
GEN-2002-002 Not reported n/r 50 Gas Withdrawn
GEN-2019-022 Not reported 115 41 Solar Withdrawn
GEN-2024-SR14 Not reported 115 36 Battery Active
GEN-2008-101 Not reported n/r 34.2 Solar Withdrawn
GEN-2012-022 Not reported 115 30 Solar Withdrawn
GEN-2024-273 Not reported 115 16.2 Solar Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.