SPP request GEN-2024-SR14

SPP queue ID GEN-2024-SR14

Queue request GEN-2024-SR14 was listed in the SPP interconnection queue at the end of 2025 as a 36 MW battery project in Lea County, NM, according to Berkeley Lab’s queue data file. The filing names Cunningham as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of April 1, 2026.

Queue IDGEN-2024-SR14
Project nameNot reported
Status (as published)Active
SubstationCunningham
Point of interconnectionCunningham 115kV
CountyLea
StateNM
Voltage115 kV
Capacity36 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2026-04-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Cunningham substation: 2 requests in the SPP queue, 2 active totaling 108 MW.

Queue IDProjectMWResourceStatus
GEN-2023-GR4Not reported72SolarActive

Lea, NM: 78 requests in the SPP queue, 22 active totaling 4,552 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityXcel/SPS
ClusterSurplus; 05 SOUTHWEST
Interconnection serviceERIS
Project typeSurplus
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)IA FULLY EXECUTED/ON SCHEDULE
Queue date2024-07-08

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.