Kay, OK interconnection queue
14 active projects totaling 1,903.2 MW in the SPP queue, plus 9 with terminal status (shown grayed).
14active projects
1,903.2active MW
23total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| GEN-2024-GR6 | Not reported | 345 | 300 | Wind | Active |
| GEN-2012-032 | Not reported | 345 | 299 | Wind | Operational |
| GEN-2023-211 | Not reported | 345 | 250 | Hybrid | Withdrawn |
| GEN-2015-001 | Not reported | 345 | 200 | Wind | Operational |
| GEN-2015-034 | Not reported | 345 | 200 | Wind | Operational |
| GEN-2016-022 | Not reported | 345 | 151.8 | Wind | Operational |
| GEN-2018-071 | Not reported | 345 | 151 | Battery | Active |
| GEN-2018-072 | Not reported | 345 | 151 | Battery | Active |
| GEN-2016-148 | Not reported | 138 | 150 | Wind | Withdrawn |
| GEN-2024-334 | Not reported | 345 | 124 | Gas | Active |
| GEN-2012-041 | Not reported | 345 | 121.5 | Gas | Operational |
| GEN-2008-071 | Not reported | 138 | 76.8 | Wind | Withdrawn |
| GEN-2012-040 | Not reported | 138 | 76.5 | Wind | Withdrawn |
| GEN-2016-071 | Not reported | 138 | 64.6 | Wind | Active |
| GEN-2009-025 | Not reported | 69 | 59.8 | Wind | Operational |
| GEN-2022-SR6 | Not reported | 69 | 50 | Battery | Withdrawn |
| GEN-2023-SR3 | Not reported | 69 | 50 | Battery | Withdrawn |
| GEN-2024-SR17 | Not reported | 138 | 50 | Battery | Active |
| GEN-2016-009 | Not reported | 69 | 29 | Gas | Operational |
| GEN-2015-035 | Not reported | n/r | 22 | Gas | Withdrawn |
| GEN-2014-022 | Not reported | 345 | 15 | Wind | Withdrawn |
| GEN-2015-028 | Not reported | 69 | 3 | Wind | Withdrawn |
| GEN-2016-031 | Not reported | 345 | 1.5 | Wind | Operational |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.