Queue IDProjectkVMWResourceStatus
GEN-2024-140 Not reported 345 250 Solar Active
GEN-2024-372 Not reported 161 250 Battery Active
GEN-2024-179 Not reported 161 199 Battery Withdrawn
GEN-2024-188 Not reported 161 199 Battery Withdrawn
GEN-2018-037 Not reported 161 100 Battery Suspended
GEN-2021-039 Not reported 161 100 Battery Active
GEN-2025-SR20 Not reported n/r 100 Other Active
GEN-2020-043 Not reported 161 56.5 Gas Operational
GEN-2020-044 Not reported 161 56.5 Gas Operational
GEN-2020-045 Not reported 161 56.5 Gas Operational
GEN-2020-046 Not reported 161 56.5 Gas Withdrawn
GEN-2020-047 Not reported 69 56.5 Gas Withdrawn
GEN-2020-048 Not reported 161 56.5 Gas Withdrawn
GEN-2020-049 Not reported 161 56.5 Gas Withdrawn
GEN-2020-050 Not reported 161 56.5 Gas Withdrawn
GEN-2017-198 Not reported 69 11.6 Battery Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first