Substation Scout

Cherokee, KS interconnection queue

4 active projects totaling 552.1 MW in the SPP queue, plus 4 with terminal status (shown grayed).

4active projects
552.1active MW
8total filed
Queue IDProjectkVMWResourceStatus
GEN-2004-017 Not reported 161 250 Gas Operational
GEN-2020-079 Not reported 161 225 Hybrid Active
GEN-2023-194 Not reported 161 225 Solar Withdrawn
GEN-2023-004 Not reported 161 200 Hybrid Withdrawn
GEN-2023-191 Not reported 138 74 Battery Withdrawn
GEN-2003-010 Not reported n/r 50 Gas Withdrawn
GEN-2014-028 Not reported 161 50 Gas Operational
GEN-2024-GR4 Not reported n/r 27.1 Other Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.