Bowie, TX interconnection queue

5 active projects totaling 900 MW in the SPP queue, plus 7 with terminal status (shown grayed).

5active projects
900active MW
12total filed
Queue IDProjectkVMWResourceStatus
GEN-2023-212 Not reported 345 400 Hybrid Withdrawn
GEN-2024-025 Not reported 345 300 Solar Active
GEN-2020-054 Not reported 345 298 Solar Active
GEN-2017-088 Not reported 345 200 Solar Withdrawn
GEN-2023-080 Not reported 345 200 Hybrid Withdrawn
GEN-2018-003 Not reported 138 150 Solar Active
GEN-2023-137 Not reported 138 150 Battery Withdrawn
GEN-2018-088 Not reported 345 130 Solar Withdrawn
GEN-2024-241 Not reported 345 100 Solar Active
GEN-2018-087 Not reported 345 75 Battery Withdrawn
GEN-2020-055 Not reported 345 71 Battery Withdrawn
GEN-2023-135 Not reported 345 52 Solar Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.