Southern Company request 25-IC-1347
Southern Company queue ID 25-IC-1347
Queue request 25-IC-1347 was listed in the Southern Company interconnection queue at the end of 2025 as a 198.9 MW solar project in Escambia County, AL, according to Berkeley Lab’s queue data file. The filing names Bucks SS - North Brewton Line as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of May 31, 2028.
| Queue ID | 25-IC-1347 |
|---|---|
| Project name | Not reported |
| Status (as published) | Active |
| Substation | Bucks SS - North Brewton Line |
| Point of interconnection | Bucks SS - North Brewton 230 kV Line |
| County | Escambia |
| State | AL |
| Voltage | 230 kV |
| Capacity | 198.9 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Proposed online date | 2028-05-31 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Bucks SS - North Brewton Line substation: 9 requests in the Southern Company queue, 3 active totaling 477.9 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| 25-IC-1376 | Not reported | 199 | Solar | Active |
| IC-1051 | Not reported | 80 | Solar | Suspended |
| IC-844 | Not reported | 300 | Hybrid | Withdrawn |
| IC-1065 | Not reported | 150 | Solar | Withdrawn |
| IC-1277 | Not reported | 150 | Solar | Withdrawn |
| IC-1278 | Not reported | 150 | Solar | Withdrawn |
| IC-487 | Not reported | 98 | Solar | Withdrawn |
| IC-746 | Not reported | 80 | Solar | Withdrawn |
Escambia, AL: 15 requests in the Southern Company queue, 5 active totaling 598.9 MW.
Tracked changes
Not tracked. Southern Company rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | Southern Company |
|---|---|
| Interconnection service | ERIS |
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | Cluster Study |
| Queue date | 2025-04-16 |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.