Sumter, GA interconnection queue
5 active projects totaling 1,407 MW in the Southern Company queue, plus 8 with terminal status (shown grayed).
5active projects
1,407active MW
13total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| IC-652 | Not reported | 500 | 615 | Solar | Active |
| IC-695 | Not reported | 500 | 250 | Solar | Active |
| IC-696 | Not reported | 500 | 250 | Solar | Active |
| IC-839 | Not reported | 230 | 200 | Hybrid | Active |
| IC-978 | Not reported | 230 | 180 | Hybrid | Withdrawn |
| IC-445 | Not reported | 230 | 152 | Solar | Withdrawn |
| IC-446 | Not reported | 230 | 152 | Solar | Withdrawn |
| IC-447 | Not reported | 230 | 152 | Solar | Withdrawn |
| IC-368 | Not reported | 230 | 100 | Solar | Withdrawn |
| 25-IC-1387 | Not reported | 115 | 92 | Hybrid | Active |
| IC-466 | Not reported | 115 | 60 | Solar | Withdrawn |
| IC-597 | Not reported | 115 | 60 | Solar | Withdrawn |
| IC-316 | Not reported | 46 | 14 | Solar | Withdrawn |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Southern Company before relying on these figures.
Site Scanner