Queue request IC-696 was listed in the Southern Company interconnection queue at the end of 2025 as a 250 MW solar project in Sumter County, GA, according to Berkeley Lab’s queue data file. The filing names Fortson - North Tifton Line as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of April 1, 2023.

Queue IDIC-696
Project nameNot reported
Status (as published)Active
SubstationFortson - North Tifton Line
Point of interconnectionFortson - North Tifton 500 kV Line
CountySumter
StateGA
Voltage500 kV
Capacity250 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2023-04-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Fortson - North Tifton Line substation: 3 requests in the Southern Company queue, 3 active totaling 1,115 MW.

Queue IDProjectMWResourceStatus
IC-652Not reported615SolarActive
IC-695Not reported250SolarActive

Sumter, GA: 13 requests in the Southern Company queue, 5 active totaling 1,407 MW.

Tracked changes

Not tracked. Southern Company rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilitySouthern Company
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Queue date2018-05-03

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first