Southern Company request IC-696
Southern Company queue ID IC-696
Queue request IC-696 was listed in the Southern Company interconnection queue at the end of 2025 as a 250 MW solar project in Sumter County, GA, according to Berkeley Lab’s queue data file. The filing names Fortson - North Tifton Line as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of April 1, 2023.
| Queue ID | IC-696 |
|---|---|
| Project name | Not reported |
| Status (as published) | Active |
| Substation | Fortson - North Tifton Line |
| Point of interconnection | Fortson - North Tifton 500 kV Line |
| County | Sumter |
| State | GA |
| Voltage | 500 kV |
| Capacity | 250 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Proposed online date | 2023-04-01 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Fortson - North Tifton Line substation: 3 requests in the Southern Company queue, 3 active totaling 1,115 MW.
Sumter, GA: 13 requests in the Southern Company queue, 5 active totaling 1,407 MW.
Tracked changes
Not tracked. Southern Company rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | Southern Company |
|---|---|
| Interconnection service | NRIS |
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | IA Executed |
| Queue date | 2018-05-03 |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.