Substation Scout

PJM_MECS substation interconnection queue

10 active projects totalling 474 MW in the PJM queue.

10active projects
474active MW
10total filed
Queue IDProjectkVMWResourceStatus
811080 PJM_MECS n/r 100 Not reported Confirmed
811046 PJM_MECS n/r 50 Not reported Confirmed
811048 PJM_MECS n/r 50 Not reported Confirmed
811061 PJM_MECS n/r 50 Not reported Confirmed
811071 PJM_MECS n/r 50 Not reported Confirmed
811075 PJM_MECS n/r 50 Not reported Confirmed
811082 PJM_MECS n/r 50 Not reported Confirmed
811073 PJM_MECS n/r 27 Not reported Confirmed
811074 PJM_MECS n/r 27 Not reported Confirmed
811067 PJM_MECS n/r 20 Not reported Confirmed

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.