Jefferson - Hanging Rock substation interconnection queue

0 active projects totaling 0 MW in the PJM queue, plus 2 with terminal status (shown grayed).

2 PJM queue filings name Jefferson - Hanging Rock as the point of interconnection, all in KY.

Target commercial operation dates as filed run from Dec 2027 to Dec 2028 (2 filings).

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
AH2-351 Jefferson - Hanging Rock 765 kV 765 600 Solar Withdrawn Dec 2027
AH2-353 Jefferson - Hanging Rock 765 kV 765 600 Solar Withdrawn Dec 2028

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.