Hopkins substation interconnection queue

0 active projects totaling 0 MW in the PJM queue, plus 7 with terminal status (shown grayed).

7 PJM queue filings name Hopkins as the point of interconnection, all in WV.

Target commercial operation dates as filed run from Mar 2024 to Jun 2025 (7 filings).

Transmission owner as filed: AEP (1 filing).

0active projects
0active MW
7total filed
Queue IDProjectkVMWResourceStatusTarget COD
AH1-451 Hopkins 138 kV 138 108 Solar Withdrawn May 2025
AH1-189 Hopkins 138 kV 138 84 Solar Withdrawn Jun 2025
AH2-191 Hopkins 138 kV 138 63 Hybrid Withdrawn Mar 2024
AH2-207 Hopkins 138 kV 138 57 Hybrid Withdrawn Mar 2024
AI2-331 Hopkins 138 kV 138 42.8 Solar Withdrawn May 2025
AI1-116 Hopkins 138 kV 138 42 Solar Withdrawn Sep 2024
AI1-117 Hopkins 138 kV 138 36 Solar Withdrawn Sep 2024

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.