Williams, OH interconnection queue

1 active project totalling 29.4 MW in the PJM queue, plus 6 with terminal status (shown greyed).

1active projects
29.4active MW
7total filed
Queue IDProjectkVMWResourceStatus
AH1-764 Not reported n/r 148 Hybrid Withdrawn
AF2-321 Stryker-Ridgeville 138 kV 138 88.8 Solar Withdrawn
AG1-056 Stryker-Ridgeville 138 kV 138 32.4 Solar Withdrawn
AE2-181 Montpelier Solar 69 29.4 Solar In Service
AI2-221 Snyder 69 kV II 69 17.7 Solar Withdrawn
AG2-377 West Unity – Exit 2/Holiday City Tap 69 kV 69 13.5 Solar Withdrawn
AF2-386 Bryan 69 kV 69 6.3 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.